A5 JACK’S HILL Multi-Disciplinary Project - Update Bulletin 2 – 29.1.2020

Dear Member

Please find attached the latest update report received on the A5 work going on overnight.


Update Bulletin 2 – 29.1.2020

Works to our essential maintenance scheme on the A5, between Tove roundabout (A43) and Weedon, started on Monday 13th January 2020 as planned.

We are currently working in Phase 1, which runs northwards from Tove roundabout (A43) to the Banbury Lane / Butcher’s Lane crossroads in Foster’s Booth.

Works carried out to date in Phase 1 include: vegetation clearance, tree removal, clearing grass and vegetation from footpaths, CCTV surveys of existing drainage pipelines, repairs to pipelines using trenchless technology, trial holes to locate mains and services, re-forming roadside ditches and breaking out existing kerb lines to replace them with an integral kerbing and drainage system.

These works, together with repairs to pipelines by excavating trenches, installation of new pipelines and headwalls to those pipelines where they enter ditches, will continue in Phase 1 for the next few weeks.

Vegetation clearance, tree removal, CCTV surveys of existing drainage pipelines and repairs to pipelines using trenchless technology started this week in Phase 2, which runs from Banbury Lane / Butchers’s Lane crossroads in Foster’s Booth to Northampton Road (Litchborough). Excellent progress to site clearance and tree removal in Phase 1 has resulted in Phase 2 starting earlier than planned. These works in Phase 2 will continue for the next few weeks.

NB: Phases 1 and 2 will now run concurrently for the next few weeks but, access across the A5 at the Banbury Lane / Butchers’s Lane crossroads in Foster’s Booth will be maintained. These particular works will be carried out overnight between 8pm and 6am Mondays to Fridays inclusive.

In an effort to reduce the environmental impact of our works, cordless electric STIHL chainsaws are in the process of being purchased by our specialist contractor. These chainsaws are particularly intended for use in residential areas due to their reduced operational noise levels.

Please note that we are planning to carry out a road crossing of the A5 in Phase 1, just south of the Banbury Lane / Butchers’s Lane crossroads in Foster’s Booth, over one weekend.

These works, to install a new surface water drain, are currently planned to take place between 8pm Friday 14th February and 6am Monday 17th February 2020.

Please note that the A5, between Tove roundabout (A43) and Weedon, will remain open as usual when we are not working and winter maintenance work, i.e. gritting of the road, will be carried out as normal.

Please also note that all our planned road works may be subject to change due to weather conditions or unforeseen circumstances.

Local businesses will be open as usual during these essential works so please continue to use these and ask others to do the same. I’m sure that your local business community would appreciate it.

I apologise for any disruption our works may cause. Please plan ahead and allow extra time for your journey.

For further information, please contact: Mike Healy, Public Liaison Officer – Working on behalf of Highways England

05/02/2020

News & Events

July 2024

June 2024

May 2024

April 2024

March 2024

February 2024

January 2024

December 2023

November 2023

October 2023

September 2023

August 2023

July 2023

June 2023

May 2023

April 2023

March 2023

February 2023

January 2023

December 2022

November 2022

October 2022

September 2022

August 2022

July 2022

June 2022

May 2022

April 2022

March 2022

February 2022

January 2022

December 2021

November 2021

October 2021

September 2021

August 2021

July 2021

June 2021

May 2021

April 2021

December 2020

November 2020

October 2020

September 2020

August 2020

July 2020

May 2020

April 2020

March 2020

February 2020

January 2020

December 2019

November 2019

October 2019

September 2019

August 2019

July 2019

June 2019

May 2019

April 2019

March 2019

February 2019

January 2019

December 2018

November 2018

October 2018

September 2018

August 2018

July 2018

May 2018

April 2018

March 2018

February 2018

January 2018

December 2017

November 2017

October 2017

September 2017

August 2017

July 2017

June 2017

May 2017

April 2017

March 2017

February 2017

January 2017

December 2016

November 2016

October 2016

September 2016

August 2016

April 2016

Not receiving Email Newsletters?

  • Login and check you email address is correct.
  • Contact Us if you changed your email address.
  • Check you spam/junk folders (and mark the message as "not spam/junk" if you find it there).
  • Add "cornhillsquash@no-reply.mycourts.co.uk" to your Contacts list or email address book.
  • Contact your email service provider and ask them why you're not receiving messages sent from cornhillsquash@no-reply.mycourts.co.uk.

Hotmail/Outlook Users

  • Login to your Hotmail/Outlook account.
  • Click Settings > View all Outlook settings > Junk Email
  • Add "mycourts.co.uk" and "no-reply.mycourts.co.uk" to your Safe Senders and domains.

GMail Users

  • Go to Gmail Settings > Filters and Blocked Addresses. If "Cornhill Squash Club <cornhillsquash@no-reply.mycourts.co.uk>" appears in the list of blocked addresses, select "Cornhill Squash Club <cornhillsquash@no-reply.mycourts.co.uk>" and click "unblock selected addresses".

Other email service providers may have similar settings -- please follow their instructions. If not, contact their support desk and request delivery of messages from cornhillsquash@no-reply.mycourts.co.uk.

mycourts ® is a Registered Trademark of HBI Consulting Ltd
Copyright © 2005-2024 HBI Consulting Ltd